INTRODUCTION
Rockmax Proof H1 is a two component polymer modified highly flexible cementitious waterproofing system with excellent elongation and good adhesion to substrate especially for critical waterproofing area and under hydrostatic pressure area. The cured material provides waterproofing membrane and permanently waterproofing.
AREA OF USES
ADVANTAGES
APPLICATION AND INSTALLATION
PREPARATION
Concrete substrate must be sound, clean, free from oil, grease, mould oil, dust, loose particles and cement paste. Ensure the surface is dry and free from water saturated. Check and investigate void, honeycomb, or crack on concrete substrate. All damaged must be repair prior to application.
Special render mortar or special masonry must be check bonding strength of Rockmax Proof H1 to ensure achieve the require strength.
MIXING
Mixer must use low speed drill mixer (500 rpm) with and including good quality steel paddle. Make sure all tools and equipments are in good conditions and clean.Add Rockmax Proof H1 part A (powder) into part B (Liquid) slowly while continue mixing. Mix approximate 3 to 5 minute until homogeneous. Do not add more water to rework.
APPLICATION
Apply Rockmax Proof H1 by plastic brush on prepared surface with approximate 0.5-1.0mm per coat. Allow the first coat to dry approximate 2-4 hours the start second coat. Apply second coat in crossing direction with first coat. Allow second coat to dry at 2-4 hours before start curing.
CURING
Allow Rockmax Proof H1 curing by spray clean water with approximate 2-3 days after dry. Keep Rockmax Proof H1 moist to prevent rapid drying up. Protect the area from damaged before finishing or tiling.
PACKAGING
36kg set.
Part A: 18kg and Part B: 18kg
STORAGE
Storage in shade and dry condition. Avoid from frost, water, moisture and high temperature .